Guyana Ready For Electricity Delivery From Ship.

Photo credit: Guyana Governement information service. She power ship has arrived in the Berbice River.
- Advertisement -

Guyana is dealing with its shortage of electricity generating plant by a novel plan–using a generator ship to pump extra amps into the local power network.

The final work to connect the Guyana Power and Light Inc’s Demerara-Berbice Interconnected System  to a power ship leased from a Turkish company started on Sunday as the vessel,  which can generate 36 megawatts of electricity, arrived on Saturday afternoon and dropped anchor in the Berbice River.

Now it is just waiting for pile driving to be completed at the location so it can be pinned in a fixed position and will not wiggle around in the current.

Present at the location to see the incoming of the ship was Zone Manager of GPL, Berbice Ravindra Jagnandan. He said his team of engineers and other technical officers had been working for fourteen days straight to make sure all the prep work for the ship was done on time.

However, due to some rough weather, the team had faced some delays. Nevertheless, he said, the team managed to complete over 90 percent of the work, with just the pile driving and the setting up of transmission lines left to be done.

Hooking up the power lines to the ship.

Additional lighting round the boundaries of the compound which leads to the ship’s mooring is also being installed.

“Once the ship is docked we have to connect the ship to our 69 kilovolts network. When that is finished, we have some more maintenance work to do on our transmission lines and then we can inject power into the grid from the ship,” Jagnandan explained to media operatives who were also present.

He noted that this will be done as soon as possible depending on the change of weather.

The manager further explained that the vessel comes with conductors which will then be connected to the transmission line ‘structure.’

“The ship comes with conductors which I think is about 100 metres. So, we will make the necessary connections from the gantry on the ship on to our transmission line structure and that will be the final stage of the operation. That could be done within two days,” the zone manager stated.

He posited that GPL will be able to transport all 36 megawatts from the ship to its network as frequently as is needed once everything is completed.

The ship is expected to become fully operationalised by May 8, 2024. It is expected too that it will operate at 96 per cent availability.

Meanwhile, Executive Director of Operations (CDO) of Karpowership International from Turkey, the company which the ship is being rented from, Osman Yalman noted that the vessel consists of two engines which will push maximum amount of power.

“The power ship have two engines which produce 18.5 megawatts each and  which will be supply to the grid,” Yalman stated.

In order to bring relief to citizens and meet the high demand of electricity in the country, the government through GPL signed a multi-million-dollar contract with Urbacon Concessions Investments, W.L.L (UCI), a subsidiary of UCC Holdings in Qatar, in collaboration with Karpowership International to rent the ship for two years.

GPL signed the contract on April 13 and has already paid a mobilisation fee of US$1 million for the vessel’s rental. The company will pay US 6.62 cents per kilowatt hour as a monthly charter fee for the powership, and a maintenance fee of 0.98 US cents per kWh, based on electricity generated.

Source: Guyana Government Information Service.
- Advertisement -