Installation begins on new 3.85 megawatt-Wӓrtsilӓ generator

From Nevis Island Administration

 

CHARLESTOWN, Nevis – Installation of the new 3.85 megawatt-Wӓrtsilӓ generator at the Prospect power plant has commenced. The US$5 million engine arrived on Nevis June 24 after being shipped by the Finland manufacturers April 20.

The Honourable Alexis Jeffers, the minister responsible for public utilities in the Nevis Island Administration (NIA), made the announcement June 26 in a further update on the status of the installation process for the new engine

Some months ago, the Nevis Electricity Company Limited (NEVLEC), with support from the NIA, purchased the engine in a bid to provide a more reliable supply of energy on the island. The new engine is expected to be installed by July 22 and ready for the testing phase.

Jeffers said he is pleased so far with progress and thanked the public for their patience. Meantime, he noted that significant work has been done on other generators at the power plant they were force to put off grid.

“We have made significant improvement with some of the difficulties we had on a couple of the Mirrlees [Blackstone] generators,” he said. “Currently, work is being done to rebuild one of the generators that had an issue with the crank shaft. That is almost there. I believe, in the next two weeks, they should be done with the complete rebuilding of that engine.”

 